STEEL TRANSMISSION LINE TOWER & HOT ROLLING MILL TO PRODUCE STEEL SECTIONS

The project report includes Present Market Position and Expected Future Demand, Market Size, Statistics, Trends, SWOT Analysis and Forecasts. Report provides a comprehensive analysis from industry covering detailed reporting and evaluates the position of the industry by providing insights to the SWOT analysis of the industry.

We can prepare PROJECT REPORT as per your INVESTMENT PLAN for BANK LOAN REQUIREMENT and INDUSTRY ANALYSIS. All reports are prepared by highly qualified consultants and verified by a panel of experts.

Have Query? Click Here to Chat
Industry Expert is Online, Chat with him for more detail.

             The   transmission  line  towers  are  comparatively   light structures  and the maximum wind pressure is the  main  criterion for  their design.  The concurrence of earth quake &  intensified wind pressures may also be considered in the earth quake –  prone areas for design of the overhead transmission line towers.  These towers  are  fabricated  by means of  bolted  joints  only.   The structural  steels  of well specified quality only  are  used  in construction   of   transmission  line  towers  to   ensure   the permissible   stresses  and  other  design  details.    Practices followed in material selection, design, fabrication, testing  and must suit the field conditions of this country.

Various  design considerations are adopted in the design  of self-supporting  steel lattice towers for  overhead  transmission lines,   including  loads,  combination  of  loads,   permissible stresses, wind pressures likely to be experienced during  service and atmospheric corrosion intensity.

Project Report Covers:

Introduction
Uses and Applications
Properties
Market Survey with future aspects
Present Manufacturers
B.I.S. Specifications
Manufacturing Process with Formulae
Cost Economics with Profitability Analysis
Capacity
Land & Building Requirements with Rates
List & Details of Plant and Machinery with their Costs
Raw Materials
Details/List and Costs
Power & Water Requirements
Labour/Staff Requirements
Utilities and Overheads
Total Capital Investment
Turnover
Cost of Production
Break Even Point
Profitability
Land Man Ratio
Suppliers of Plant & Machineries and Raw Materials.

Additional information

Plant Capacity

25 days/month

Land and Building

Area 5 Acres Rs. 200.00 (Figures in Lacs)

Plant & Machinery

Rs. 600.00 (Figures in Lacs)

Working Capital 3 Months

Rs. 4,981 Figures in Lacs

Total Capital Investment

5,981 Figuresin Lacs

Rate of Return

34%

Break Even Point

38%